What the Town of Windsor asks for when you finish a basement: the permit, the plans, and the code items inspectors check, from the Town's own 2024 handout.

Permit even if you DIY2024 IRC since Jan 1, 2026Alarms hard-wired, interconnected

What does it take to finish a basement in Windsor?

A Town of Windsor building permit, even if you do all the work yourself. Plans must show the whole basement, with room uses, alarms, electrical, plumbing, mechanical equipment and windows. Since January 1, 2026 plans are reviewed under the 2024 International Codes, and SAFEbuilt inspects the work for the Town. There is no Town contractor license, but electricians and plumbers need a State of Colorado license.

Source: Town of Windsor: FAQs, Building Permits, Basement Finish handout.

The steps, in order

  1. Test for radonBefore framing. Free test kits are available from the Colorado Department of Public Health and Environment.
  2. Draw the plansA floor plan to scale of the whole basement, with the items listed below.
  3. Apply in Community CoreThe Town's online permit system. A personalized login is emailed on request; card payments carry a 3% fee.
  4. Build and call for inspectionsSAFEbuilt inspects for the Town (970-674-1036). Requests by 3:00 p.m. Monday to Thursday are scheduled for the next working day.
  5. Keep the permit activeA permit expires if work doesn't begin within 180 days or stops for 180 days.
  6. Final inspection, then final paymentPay your contractor in full only after the final inspection or Certificate of Occupancy.

Sources: Town of Windsor Building Permits, FAQs and Basement Finish handout; radon kits: Larimer County Health.

What the plans must show

  • The layout of the entire basement, to scale, with the use of every room; existing versus new, finished versus unfinished.
  • Electrical outlets, smoke detectors, lighting, fans, plumbing changes and cleanouts, the furnace and water heater, and whether they are gas or electric.
  • Window sizes and types, with the emergency escape and rescue windows identified.
  • Changes to the structure, such as posts, beams and floor joists.
  • Dropped ceiling areas under 7 ft, and clearances around the tub and fixtures.

Source: Town of Windsor / SAFEbuilt, 2024 IRC Residential Basement Finish, page 1.

Code items inspectors check

ItemRequirement
Smoke alarmsIn all basements; with a bedroom, in the bedroom and within 15 ft outside it. Added alarms hard-wired with battery backup and interconnected; required in new and existing bedrooms, halls and on each level
CO alarmsOutside each sleeping area, within 15 ft of the bedrooms; battery, plug-in or hard-wired combination units
Furnace and water heater30 in. clear working space in front; not in a bedroom or bathroom unless sealed with outdoor combustion air
Fire blockingIn furred walls at the ceiling, every 10 ft, and at soffits and dropped ceilings
Space under stairsIf enclosed and usable, 1/2 in. gypsum board on walls and ceiling
Toilet clearance21 in. in front; 15 in. from center to side
Shower sizeAt least 900 sq in. inside
Bathroom fanRequired where the window doesn't open; vented outdoors, not within 3 ft of an opening
Ceilings under 7 ftConsult the Building Department

Source: Town of Windsor / SAFEbuilt, 2024 IRC Residential Basement Finish (published January 1, 2026), page 2. For wall insulation minimums the handout says to check with the Building Department.

Basement utility room with a furnace, ductwork and exposed pipes

Plan around the mechanicals. The 30 in. working space in front of the furnace and water heater, and the rule that each can be serviced or removed without disturbing the other or the walls, often decide where the walls of a new room can go.

Local factors

Young homes. The median Windsor home was built in 2009 (ACS 2020-2024), so many basements are unfinished shells in newer houses with modern wiring. Builders must permit a basement finish separately from the house.

Soils. The Colorado Geological Survey flags wind-blown sediments in the Windsor area that can collapse when wet. Keep window wells draining and water away from the foundation. Source: CGS, Windsor quadrangle.

Radon. Windsor spans Larimer and Weld counties. Larimer County's average indoor level is 7.8 pCi/L; the EPA advises mitigation at 4 pCi/L or more. Source: Larimer County Health.

What it costs

The Census Bureau counts Windsor in the Greeley metro area, so our Greeley basement cost calculator uses the closest wage data. For the permit fee, the Town offers estimates on request through its building permits page.

Common questions

Do I need a permit to finish my own basement in Windsor?
Yes. The Town says finishing a basement requires a building permit even if you are doing all the work yourself, so it can inspect the work against the adopted building code.
Does my contractor need a Windsor license?
No Town contractor license is required. Electrical and plumbing contractors must hold a current State of Colorado license and send it to the Town.
Can a builder include the basement finish in a new home permit?
No. The Town says builders cannot include basement finishes in their master plans; the finish needs its own permit.
When should I make the final payment to my contractor?
The Town's handout advises not to make final payment until you have a Certificate of Occupancy or the final inspections have passed, and to have the contractor apply for the permits.