What does it take to finish a basement in Loveland?
A City of Loveland building permit: basement finishes are on the City's list of projects that need one. You can do the work yourself on your primary residence with a homeowner affidavit. Expect 20 to 30 working days of plan review per round, a fee based on the project's valuation plus 65% for plan review, and inspections recorded on a card posted at the house. A new basement bedroom needs an escape window, and radon testing comes first: Larimer County averages 7.8 pCi/L.
Source: City of Loveland Permitting FAQs, 2026 fee schedule, 2024 IRC amendments; Larimer County Health.
The steps, in order
- Test for radonIdeally in winter, before framing, so a mitigation system can be planned in. Larimer County and the State offer free test kits.
- Decide who does the workYourself, on your primary residence, with a homeowner affidavit; or a contractor. To check a contractor's City license, call 970-962-2505.
- Draw the plans and applyComplete the residential forms for a basement finish and email them to the Building Division. Plan review takes 20 to 30 working days per round.
- Pay the feesThe permit fee is based on project valuation (ICC data); residential plan review adds 65% of the permit fee. You can request a fee estimate first.
- Post the inspection cardWork can't start until the inspection record card is posted where the inspector can sign it, with the address visible from the street.
- Call for inspectionsThe inspector approves each stage or lists what to fix. Keep the card on site until the final approval.
Sources: Permitting FAQs; Fees; 2026 fee schedule; IRC amendment R109.1; Larimer County Health.
Rules and fees at a glance
| Item | Loveland |
|---|---|
| Permit | Required for a basement finish |
| Building code | 2024 IRC with local amendments, since July 1, 2026 |
| Doing your own work | Primary residence, homeowner affidavit |
| Plan review time | 20 to 30 working days per round |
| Permit fee | Based on ICC building valuation data |
| Plan review fee | 65% of the permit fee |
| Permit lapses | 180 days without work |
Sources: City of Loveland Permitting FAQs, Building Division, fee schedule, Ordinance 6817.
Adding a bedroom

Under Loveland's 2024 amendments, a new sleeping room created in an existing basement needs an emergency escape and rescue opening, such as an egress window. Other basement alterations, like a family room or a bathroom, don't trigger that requirement.
For new construction, the amendments also add a heat detector in the garage tied into the home's smoke and CO alarms, so that if one sounds, they all do. Ask the Building Division which alarm rules apply to your finish when you apply.
Source: Loveland IRC amendments, sections R310.7 and R310.2.1.
Local factors
Radon. Larimer County reports an average indoor radon level of 7.8 pCi/L against a national 1.3 pCi/L, and the EPA advises mitigation at 4 pCi/L or more. Loveland's passive radon rule covers new homes and large additions, not basement finishes, so testing is up to you. Source: Larimer County Health.
Soils. The Colorado Geological Survey lists swelling and collapsing soils, over the Pierre Shale and wind-blown sediments, among the Loveland area's main natural hazards. Basements over swelling soils can move; keep water away from the foundation. Source: CGS, Loveland quadrangle.
Older homes. 34.1% of Loveland homes were built before 1980 (ACS 2020-2024), and older basements more often need wiring, insulation and egress upgrades.
Rebates. Loveland Utilities electric customers can get insulation and air-sealing rebates through an Efficiency Works certified provider. Source: Loveland Water and Power.
What it costs
Loveland shares a labor market with Fort Collins (the Fort Collins-Loveland metro area), so our basement cost calculator uses the right wage data. Loveland's permit fee differs from Fort Collins' flat fee: it follows project valuation, so request a fee estimate from the City.