What should I check before each basement inspection in Fort Collins?
Prepare rough (gas, plumbing, mechanical, electrical, framing), then insulation (before drywall), then final. The list below turns the City's guide into checks for each stage.
Source: City of Fort Collins Basement Finish Guide, pages 2, 4 and 5.
Before you apply
- Test the basement for radon (Larimer County average 7.8 pCi/L; EPA action level 4 pCi/L).
- Choose a contractor with a City of Fort Collins license (A, B, B(DR), C1, C2, D1, D2, D(DR) or E residential).
- If the home has fire sprinklers, contact the City before applying ([email protected]).
- Get stamped structural plans if you will cut new foundation windows, add beams or alter structure.
- Mark each space on the plans as new or existing, and label every emergency escape opening.
Design checks
- Bedrooms: at least 70 sq ft and 7 ft in each direction.
- Ceilings: 6 ft 8 in in bedrooms, living areas and halls; 6 ft 4 in in showers, storage and laundry.
- Each bedroom has an escape opening; new below-grade windows give 5.7 sq ft net clear opening.
- New window wells drain to the foundation drain (if present) and have a clear path to the street.
- Smoke alarms inside and outside sleeping areas and on each level; CO alarm within 15 ft of bedrooms.
- Bathroom: exhaust fan ducted outside or an operable window; dedicated 20-amp GFCI circuit.
- Low-flow fixtures: toilet 1.28 gpf, shower 1.8 gpm, faucet 1.5 gpm; backwater valve on new fixtures.
- New or replacement windows: U-factor 0.28 max, SHGC 0.35 max.
Before the rough inspections
- Gas line air test, plumbing top-out and water test ready.
- Rough mechanical and rough electrical complete (AFCI, GFCI and tamper-resistant receptacles).
- Framing: pressure-treated bottom plates on concrete; fire blocking at ceilings and every 10 ft in furred walls.
- Usable space under stairs planned for ½ in drywall protection.
Before the insulation inspection
- Foundation walls insulated (R-19 continuous, or R-13 between studs + R-5 continuous, or another option in the guide).
- Rim joists insulated to R-30.
- No drywall installed yet.
Before the final inspection
- All alarms installed and working, interconnected if the home has an existing system.
- Escape windows operable, wells clear and draining.
- Mechanical room does not open into a bedroom or bathroom (or meets one of the listed exceptions).
Source: City of Fort Collins Basement Finish Guide. This checklist summarizes the guide and does not replace it; your plan reviewer may ask for more.